Birla Corporation Ltd

Birla Corporation Expansion & Cost Efficiency Updates 🏭📉

- Kundanganj Line-III commissioning planned for Q4 FY26

- Capacity expansion target: 24.2 million tonnes by FY28

- Capacity expansion target: 27.6 million tonnes by FY29

- Kiln fuel cost reduced to INR 1.47 per kg

- Premium cement volume rose to 63% of total sales

- Mukutban plant achieved record dispatches in January 2026

- Q3 volume at 6.3 lakh tonnes with clinker-to-cement ratio of 0.61

- Consolidated clinker-to-cement ratio was 1.58

- Net debt stood at INR 2,550 crores as of quarter end

- Capex for nine months was approximately INR 300 crores

- Production cost per unit decreased

- Mine acquisition in Rajasthan faced cancellation; legal options considered

- Cautious approach to RMC business, limited to Uttar Pradesh operations