🚧 Ceigall India's Ayodhya Bypass Hits 35% Completion Ahead of Schedule

- Project: Construction of 4/6 Lane Southern Ayodhya Bypass

- Physical progress: 35.00% as of May 7, 2026

- Independent Engineer verified progress via letter dated May 12, 2026

- Executed by subsidiary Ceigall Ayodhya Bypass Private Limited

- Milestone II completed 92 days ahead of schedule

- Total length: 32.172 km on NH-27 in Uttar Pradesh, India