🏗️ Dilip Buildcon receives Provisional Completion Certificate for 68.015 km NH-563 project in Telangana

- Provisional Completion Certificate received for Karimnagar-Warangal Highways project.

- Project: 4-laning of NH-563 in Telangana under Bharatmala Pariyojana.

- Design length: 68.015 km.

- Project mode: Hybrid Annuity.

- Project cost: INR 1647 Cr.

- Appointed date: 18.07.2023.

- Scheduled completion date (incl EOT): 07.09.2026.

- Provisional completion date: 07.09.2026.