Godavari Biorefineries Ltd

Godavari Biorefineries Receives NGT Directive on Environmental Measures 🏭💧

• National Green Tribunal (NGT) issued an order to Godavari Biorefineries Ltd on February 09, 2026

• Order follows a complaint filed on March 24, 2024 alleging water and air pollution from the Sakarwadi facility

• Company must construct a trench to prevent runoff from reaching the Godavari River

• Water treatment measures required to be completed within two months

• Company states no material financial, operational, or other impact from this order