- Rs. 212.20 crore raised through a preferential issue.
- Rs. 12.15 crore overutilized for working capital, exceeding the planned amount by less than 10%.
- Rs. 42.04 crore unutilized funds temporarily invested in fixed deposits with Bank of Baroda, yielding returns between 3.50% to 7.55%.
- Delays noted in utilization of second and third tranches, with some deployments ongoing beyond scheduled timelines.
- No shareholder approval obtained for reclassification of objects.
- Part of funds used in a subsidiary's account, which was not explicitly permitted.
- All government and statutory approvals related to issue objects have been obtained.
- No adverse events affecting viability reported.